| Company | Customer | Date | Announced | Executed so far | Execution % | Status | Credibility | Source |
|---|---|---|---|---|---|---|---|---|
| MAZDOCK | Indian Navy | 14 May 2026 | ₹8,400 Cr 60 mo · 52% of rev | ₹420 Cr actual billed | 5% | Executing | ✓ Reliable | 🤖 AI |
| P75I submarine programme. Execution just started — long runway ahead. | ||||||||
| BEL | MoD | 02 Apr 2026 | ₹3,200 Cr 36 mo · 28% of rev | ₹480 Cr actual billed | 15% | Executing | ⚡ Watch | 🤖 AI |
| EW systems order. MoD clearance delays are common — monitor quarterly billings. | ||||||||
| LT | NHAI | 18 Mar 2026 | ₹5,800 Cr 48 mo · 8% of rev | ₹870 Cr actual billed | 15% | Executing | ✓ Reliable | Manual |
| Highway project. L&T's execution historically reliable — on track. | ||||||||
| IRCON | Railways | 10 Jan 2026 | ₹2,800 Cr 36 mo · 22% of rev | ₹140 Cr actual billed | 5% | Delayed | 🚩 Risk | 🤖 AI |
| ⚠️ LOI — not a firm order yet. Company included in order book total. Verify before modelling revenue. | ||||||||